Week Four 8 - 12 Oct
This week was a lot more exciting culminating in the end of the first stage of building.
Day 13 - 15 The guy got rid of most of the dirt except some that they were able to use on the neighbours block. The neighbours cut is due to start by the end of the week.
This week was a lot more exciting culminating in the end of the first stage of building.
Day 13 - 15 The guy got rid of most of the dirt except some that they were able to use on the neighbours block. The neighbours cut is due to start by the end of the week.
Day 17 I went out to the block early on the way to work and the
big job had already started.
The wet barrier, reinforcing and foam waffles had already been laid on
both the upper and lower areas. The concrete pump track was there and
the guys had already started pouring the lower pad. When I went back
after work we had two complete slabs. Its very exciting and much easier
now to work out where everything is. I took the kids around and showed
them where their rooms would be etc. Although the rooms in the house
are big without the walls up its still hard to appreciate the size of
the rooms. Although I do know that the top slab of our house is about
the same size of my entire first house!!